Next DC M3 Stages 1, 2, 3, 4, 5, 6

Year:2026
Owner:NEXTDC
Builder:Kapitol Group with HDR Architect
Project:$1.5 Billion | 225 MW Major hyperscale data centre campus in West Footscray, Melbourne.
Scope:Unison supplied 1,100 metres of specialist expansion joint systems, including waterproof seals, fire-rated strips, extra-heavy-duty seismic cover plates, and roof, wall and façade seals.
Products:Aquo P; Aquo H; By NF Aq P; Dz HX; Dz H; Py I; Py B; Si R; Vt P; Vt S

Future Stages: Unison will supply a further three stages of the M3 development.  Fire seals Certified to AS 1530.4 & BS476 standards